Practical supply planning guide · Procurement

How much to order and when: a purchasing guide

A practical planning guide with an illustrative calculation, operating checks and a path from recommendation to approval.

Short answer

Calculate net requirements from demand during the protection period, safety stock and inventory position. Apply minimum orders and packaging multiples only after checking the need.

First scope

Start with one SKU and location, then validate the policy on a representative product group.

When to review

Recalculate at each planning review and whenever lead time, demand or confirmed receipts change.

Typical buyer

Supply chain, demand planning, procurement and inventory teams.

Calculation and decisions, step by step

01

Define the protection period

For periodic review, cover lead time plus the interval until the next review. Use the same unit for demand and time.

Owner
Planning and procurement
Output
Documented calculation and approved decision

02

Calculate inventory position

Add usable stock and confirmed inbound receipts within the horizon; subtract outstanding commitments not already included in demand. Exclude damaged stock and avoid counting orders twice.

Owner
Planning and procurement
Output
Documented calculation and approved decision

03

Work through the quantity

Illustrative constant-demand example: 10 units/day, 12-day lead time, 7-day review interval and 40 safety units require 230 units. With 100 usable units and 30 inbound, and no additional commitments, net need is 100. A 120-unit MOQ and packs of 24 produce an order of 120. Confirm that the extra 20 units fit storage and cash limits.

Owner
Planning and procurement
Output
Documented calculation and approved decision

04

Approve the purchase

Check supplier reliability, shelf life, available cash and safe surplus at other locations before approving an ERP purchase order.

Owner
Planning and procurement
Output
Documented calculation and approved decision

Readiness checklist

  • Demand by SKU and location, in consistent units
  • Usable stock, commitments and dated inbound receipts
  • Actual lead time, MOQ, packaging and service target

Common mistakes

  • Treating sales during stockouts as complete demand
  • Counting customer orders twice
  • Using an average lead time without checking variability

Questions to ask vendors

  1. Can I review inputs and edit a recommendation before approval?
  2. How are purchases and transfers returned to my ERP?

Success metrics

  • Fill rate: units fulfilled / units requested
  • Stockout days by SKU and location
  • Inventory value and excess inventory
  • Recommendation-to-approval time

Where SOBERAN fits

SOBERAN connects demand, inventory, purchasing constraints and human approvals. Review a real SKU-and-location workflow in a demo to confirm data and ERP integration scope.

Talk to SOBERAN

Related reading

Review your planning with one SKU and location.

Bring your demand, purchasing or replenishment process. In 30 minutes we review data, decisions and ERP integration scope.

Review this workflowVer preços

30 minutos · Sem compromisso · Traga um fluxo de trabalho

Revise um fluxo com nossa equipe — 30 minutos, sem compromisso.

Agendar demonstração